KGHM Ajax Will Not Pay More For City Review
Posted by Stop Ajax Mine on October 25th, 2016 5:26am
The company behind the proposed Ajax mine south of Kamloops will not be paying any more money toward completion of a city-commissioned study of its application.
In a letter to Kamloops council, KGHM Ajax project manager Chris Wild said the company will not offer more than the $300,000 is originally committed to fund the study by SLR Consulting.
The consultants have told council the cost of the study has exceeded the original $300,000 estimate and another $200,000 is needed for completion. SLR has cited delays in the environmental-assessment process as the reason behind the need for additional funds.
“In 2015, KAM (KGHM Ajax) agreed to support the city’s review,” Wild wrote.
“We fully honoured our commitment by providing $300,000 to the city with
no strings attached. We planned a budget for 2016; however, that is focused on completing the regulatory environmental-assessment process.”
On May 4, the B.C. Environmental Assessment Office (BCEAO) paused its 180-day review of the mine’s impacts at day 107 so KGHM Ajax can answer questions from the public, First Nations bands and other groups. SLR alone has 800 questions about the company’s application.
In September, Allan Michener, environmental services supervisor for the city, said SLR will need about $200,000 more to finish its review due to delays in the Ajax assessment process and the difficulties in getting information from the company.
“SLR has delivered on all required tasks to date; however, there has been a significant amount of effort required by SLR and city staff to work through KGHM’s application and to work with KGHM, the BCEAO and other members of the project’s technical working Group,” he wrote. “The official timeline was suspended due to technical components that needed to be worked out and significant work continues in the background to address these components.”
The BCEAO has not set a deadline by which the mining company must respond to public submissions, though Wild told council in a second letter the company expects to submit all required information “later this year.”
Comments
There are currently no comments on this blog post.
Post a Comment
RECENT POSTS
- SLR Report and Town Hall Meeti...
July 11th, 2017 11:10am - Report from Expert Panel for t...
July 11th, 2017 11:09am - Celebrate the SSN Decision on ...
July 11th, 2017 11:08am - Environmental Assessment Clock...
July 11th, 2017 11:08am - Young Scientists Evaluate Envi...
July 11th, 2017 11:06am
ARCHIVE
- July 2017
- October 2016
- July 2016
- April 2016
- March 2016
- January 2016
- December 2015
- November 2015
- September 2015
- August 2015
- July 2015
- June 2015
- May 2015
- April 2015
- March 2015
- February 2015
- January 2015
- December 2014
- November 2014
- September 2014
- August 2014
- July 2014
- June 2014
- February 2014
- August 2013
- July 2013
- June 2013
- May 2013
- April 2013
- March 2013
- February 2013
- November 2012
- October 2012
- September 2012
- July 2012
- June 2012
- May 2012
- April 2012
- March 2012
- February 2012
- January 2012
- December 2011
- November 2011
- October 2011
- September 2011
- August 2011
- July 2011
facebook.com/stopajaxmine
twitter.com/stopajaxmine