Ajax Application Delayed

Posted by Stop Ajax Mine on June 16th, 2015 12:08am

Comments from 1st quarter financial report 
 
A new campaign of drilling was commenced, comprising among others the conclusion in March 2015 of drilling within the planned open pit. The drill cores obtained will be used in further metallurgical research.

Actions were carried out aimed at submitting an application for environmental permits. 
Due to the need to conduct additional analyses related to waste storage technology, 
dictated by the results of the work of the commission set up to examine the causes of the accident at the Mt. Polley mine in British Columbia and to stricter criteria applied in 
reviewing applications by the decision-making authorities in Canada
, submission of the 
application is planned to occur in the second half of 2015.